by Raildudes dad on Thu Aug 09, 2012 10:36 pm
Lameroux is closing on Monday (if West River is back open) due to sanitary sewer work west of the crossing. Later the following week, the RR and the Rood Commission are going to work on some semi-permanent repairs to the crossing but it won't get a West River type reconstruct until 2013. The West River reconstruct was scheduled for later this year but they had a 5 foot piece of the head break out Sunday night. They are taking the super-elevation out of the crossing which will allow the Road Commission to do some milling and paving and take some of the "ski-jump" out of the crossing.