Well as if the signal projects on the Marion District and the Chicago Line are not enough, here is another one.

The entire section from PERU IN to BLAKESLEY OH is getting a PTC signal upgrade.

Every MCP outside of Fort Wayne is getting redone from scratch. That means all the remaining Wabash search lights will be going bye bye. (one exception so far)

All the intermediates, and the existing MCPs in Fort Wayne are getting PTC antennas. The MCPs of course are getting the higher dual antenna sticks.

Also I saw a higher dual stick antenna at Junction. But that one is on the ex PRR line in Fort Wayne.

Those annoying unbonded sidings on the Wabash north of Fort Wayne are finally getting track circuits.

ST Joe may keep it's searchlights for the Northbound NS. I saw no evidence of work there. (mind you who would know with all the stuff there CSX left after the BIG derailment there)

INE-KP
Railroadfan...fan
Posts: 44
Joined: Sun Mar 19, 2006 1:10 pm
Location: Angola, IN

Re: Signal Replacement/PTC Project Peru to Blakesley WABASH

Unread post by INE-KP »

CP Mode signals were upgraded a couple years back, CP Montpelier is getting new signals, plus there are a bunch of "New" installations going in along the line as well.

LakeATCS
Railroadfan...fan
Posts: 625
Joined: Sat Feb 28, 2015 5:37 am

Re: Signal Replacement/PTC Project Peru to Blakesley WABASH

Unread post by LakeATCS »

From what I am seeing via ATCS, the old signals should be gone at Peru Junction to Lagro on the Wabash.

No changes at Wabash/CP58, but those were newer signals anyway.

Replacement is underway. Get any and all photos you want of anything left. The Grim Reaper has begun.

jwilliam33
Railroadfan...fan
Posts: 136
Joined: Tue Jan 20, 2009 10:09 am

Re: Signal Replacement/PTC Project Peru to Blakesley WABASH

Unread post by jwilliam33 »

There was a new antenna installed between Munson and North Morenci a few weeks ago as well.

LakeATCS
Railroadfan...fan
Posts: 625
Joined: Sat Feb 28, 2015 5:37 am

Re: Signal Replacement/PTC Project Peru to Blakesley WABASH

Unread post by LakeATCS »

An update.

Huntington, Mardenis, West Roanoke, and East Roanoke are now cut over.

So the searchlight bracket mast should now be gone.