NE Indiana NS Chicago Line PTC project

Anything pertaining to railfanning in Indiana.
User avatar
justalurker66
Railroadfan...fan
Posts: 1964
Joined: Tue Feb 15, 2011 2:51 am

Re: NE Indiana NS Chicago Line PTC project

Unread post by justalurker66 »

CP379 Kendallville has also received a new radio tower
Old Tower
Old Tower
New Tower
New Tower
Registration Number: 1297421
Owner Name: Norfolk Southern Railway Company
Latitude/Longitude: 41-26-41.3N 085-16-09.5W
Structure City/State: Kendallville, IN
Overall Height Above Ground (AGL): 50.3 (meters)
http://wireless2.fcc.gov/UlsApp/AsrSear ... ey=2696940

User avatar
justalurker66
Railroadfan...fan
Posts: 1964
Joined: Tue Feb 15, 2011 2:51 am

Re: NE Indiana NS Chicago Line PTC project

Unread post by justalurker66 »

A quick stop in Kendallville today ... no change.

LakeATCS
Railroadfan...fan
Posts: 625
Joined: Sat Feb 28, 2015 5:37 am

Re: NE Indiana NS Chicago Line PTC project

Unread post by LakeATCS »

Looks like the Kendalville terminal lead at CP 379 is shunted on all the time now.

Not surprising. I have seen this happen on NS for interlocking being cut over to the new machines several times. Since these not 261 territory approach circuits are not vital to operation, I have seen the maintainers go ahead and pull the wires from the old interlocking machines way ahead of time. They then have one less circuit to mess with during cut over as they can connect it to the new machine ahead of time.

The River Lead at 509 was like this too. Among others.

User avatar
justalurker66
Railroadfan...fan
Posts: 1964
Joined: Tue Feb 15, 2011 2:51 am

Re: NE Indiana NS Chicago Line PTC project

Unread post by justalurker66 »

LakeATCS wrote:Looks like the Kendalville terminal lead at CP 379 is shunted on all the time now.
Which bit is that? I don't see anything shunted 100%.

Are you expecting CP 379 to be cut over soon?

LakeATCS
Railroadfan...fan
Posts: 625
Joined: Sat Feb 28, 2015 5:37 am

Re: NE Indiana NS Chicago Line PTC project

Unread post by LakeATCS »

The one for the lead on the old GR&I

K62 is the approach bit for the lead to the Kendalville Terminal. K44 is the TK bit for about a few car lengths north of the home signal for the lead.

This is because the interlocking machine is old enough to have controlled the diamonds for the GR&I/NYC crossing. The K44 TK circuit is a remant dating from then.

K62 is now on all the time, before it would only show when the NS went in there.

Notch 8
Railroadfan...fan
Posts: 460
Joined: Sun Apr 04, 2010 6:43 am

Re: NE Indiana NS Chicago Line PTC project

Unread post by Notch 8 »

LakeATCS wrote:Looks like the Kendalville terminal lead at CP 379 is shunted on all the time now.
Its always been on..

LakeATCS
Railroadfan...fan
Posts: 625
Joined: Sat Feb 28, 2015 5:37 am

Re: NE Indiana NS Chicago Line PTC project

Unread post by LakeATCS »

Not true. And I have logs to prove that from earlier this year.

User avatar
justalurker66
Railroadfan...fan
Posts: 1964
Joined: Tue Feb 15, 2011 2:51 am

Re: NE Indiana NS Chicago Line PTC project

Unread post by justalurker66 »

LakeATCS wrote:Not true. And I have logs to prove that from earlier this year.
Is it possible that there is an actual occupancy (or rail defect)?

LakeATCS
Railroadfan...fan
Posts: 625
Joined: Sat Feb 28, 2015 5:37 am

Re: NE Indiana NS Chicago Line PTC project

Unread post by LakeATCS »

No it was occupancy.

The local goes in there in the middle of the day on weekdays.

User avatar
justalurker66
Railroadfan...fan
Posts: 1964
Joined: Tue Feb 15, 2011 2:51 am

Re: NE Indiana NS Chicago Line PTC project

Unread post by justalurker66 »

You may have misunderstood ...

It it possible that there is now actual occupancy or a rail defect that is causing the occupancy indication?
When was the last time the lead was "unoccupied"?

LakeATCS
Railroadfan...fan
Posts: 625
Joined: Sat Feb 28, 2015 5:37 am

Re: NE Indiana NS Chicago Line PTC project

Unread post by LakeATCS »

Always possible, but in this case with the flashers right on that circuit south of the signal I doubt it.

The river line/lead at CP509 was like this too. It was red in the months leading up to the cut over to the new machine.

I have seen this behavior in the months up to cut over of other NS machines too. Both lake and dereborne.

I know for sure this summer it worked right. Might have too pull some logs to see now.

User avatar
justalurker66
Railroadfan...fan
Posts: 1964
Joined: Tue Feb 15, 2011 2:51 am

Re: NE Indiana NS Chicago Line PTC project

Unread post by justalurker66 »

The new (future) signal on the Kendalville Terminal lead is around the corner closer to the switch on the main line (about 400ft signal to switch instead of ~935ft). I suspect the approach circuit will be the track between the new signal and the first road crossing (Mitchell St, north of the current signal).

My last stop in Kendalville was at Thanksgiving ... no changes seen to the signals there that has not already been reported. Google has finally loaded areal pictures from last April.

LakeATCS
Railroadfan...fan
Posts: 625
Joined: Sat Feb 28, 2015 5:37 am

Re: NE Indiana NS Chicago Line PTC project

Unread post by LakeATCS »

I suspect the maintainer probably got tired of maintaining a troublesome circuit that is going away and got permission to pull the wires for the approach.

User avatar
justalurker66
Railroadfan...fan
Posts: 1964
Joined: Tue Feb 15, 2011 2:51 am

Re: NE Indiana NS Chicago Line PTC project

Unread post by justalurker66 »

The bit has been off lately. I have not been logging to see if it has been on lately, just noticing that when I looked at my display there was no occupation.

LakeATCS
Railroadfan...fan
Posts: 625
Joined: Sat Feb 28, 2015 5:37 am

Re: NE Indiana NS Chicago Line PTC project

Unread post by LakeATCS »

Ehh your right that bit has went off.

LakeATCS
Railroadfan...fan
Posts: 625
Joined: Sat Feb 28, 2015 5:37 am

Re: NE Indiana NS Chicago Line PTC project

Unread post by LakeATCS »

Things may be getting started for the year. Saw the first NS signal change of the year. MP 266 east of Toledo OH new automatics. Yeah it's ohio, but maybe they are working east to west.

User avatar
justalurker66
Railroadfan...fan
Posts: 1964
Joined: Tue Feb 15, 2011 2:51 am

Re: NE Indiana NS Chicago Line PTC project

Unread post by justalurker66 »

The installs went east to west ... having the activations go east to west makes sense. I am surprised that they didn't change over to the new signals quicker, but it is nice to see some movement.

LakeATCS
Railroadfan...fan
Posts: 625
Joined: Sat Feb 28, 2015 5:37 am

Re: NE Indiana NS Chicago Line PTC project

Unread post by LakeATCS »

Again out in ohio. I will post it here because the Ohio forum isn't that interested in ATCS stuff,

CP 267 and CP 268 being replaced. No physical changes. Just new interlocking machines.

New automatics at MP 270

New electric lock switch at 271.9

The new signals have been up at least since 10/2015. I can see the new and old signals on google earth.

User avatar
justalurker66
Railroadfan...fan
Posts: 1964
Joined: Tue Feb 15, 2011 2:51 am

Re: NE Indiana NS Chicago Line PTC project

Unread post by justalurker66 »

~85 miles from Indiana ... at a mile per day they could cross the line in around three months. (Although rural intermediates will go a lot faster than urban interlockings.) We'll have to keep a watch on the Huntington District and Marion Line and see if any of those 2015-2016 installs get activated.

The next change in Indiana on the Chicago line looks like CP 423.

User avatar
justalurker66
Railroadfan...fan
Posts: 1964
Joined: Tue Feb 15, 2011 2:51 am

Re: NE Indiana NS Chicago Line PTC project

Unread post by justalurker66 »

Any more updates working across Ohio into Indiana?