MQT3001 wrote:UPDATE:
Amtraks today detoured over the PC, as well as two intermodals.
The Amtrak Main at Porter in back up, but no signals and still hand throw.
The wrecked containers are being removed from the site currently. More than likely the site will be cleared around midday tomorrow.
Estimated Re-openings:
NS Main #1: Early Sunday
NS Main #2: Saturday evening around Midnight
NS Main #3: Midnight
MQT Main #1: Friday evening
MQT Main #2: Early Sunday
MQT3001 wrote:MQT3001 wrote:UPDATE:
Amtraks today detoured over the PC, as well as two intermodals.
The Amtrak Main at Porter in back up, but no signals and still hand throw.
The wrecked containers are being removed from the site currently. More than likely the site will be cleared around midday tomorrow.
Estimated Re-openings:
NS Main #1: Early Sunday
NS Main #2: Saturday evening around Midnight
NS Main #3: Midnight
MQT Main #1: Friday evening
MQT Main #2: Early Sunday
NS Main #3 no longer blocked...panel track is being installed. On track for the Capital Limited to be able to go thru
DT&I wrote:When can we send our trains through? They've been sitting at the junction since yesterday.
MQT3001 wrote:DT&I wrote:When can we send our trains through? They've been sitting at the junction since yesterday.
MQT main is next to cleared, but they have a ways to go. Our crews will take them for you also. However, top priority stuff, like intermodals and Amtrak will go by first, then your stuff can go. Look for some MONSTER manifests w/ extra sections getting out of GR. Holland pass has a 185 car monster that was removed from Wyoming yard to make space....we have Westbounders in every siding trying to make room inthe yard LOL
conrailman75 wrote:Hey DT&I, if MQT can't handle your trains right now, you can use Penn Central as a detour route and we can get your trains around the wreck site and back onto their home rails for ya!
DT&I wrote:conrailman75 wrote:Hey DT&I, if MQT can't handle your trains right now, you can use Penn Central as a detour route and we can get your trains around the wreck site and back onto their home rails for ya!
We'll this,thanks! But MQT, This isn't exactly making me want to keep the GR&P main in use...
DT&I wrote:Well you have to look at it from my perspective here, these trains are 3 days late now. We're getting phone calls left and right asking where their freight is. This is a complete loss of profit and we can't have that at this time so until we see fit trains will be routed over our line but the switch to yours at Michigan City will stay in place for detours.
DT&I wrote:Well the problem was the 3 trains were eastbounds, we did send some power to get the westbound and ran it down through Liberty Center and west. There are just to many trains behind them to pull them back.
MQT3001 wrote:DT&I wrote:Well the problem was the 3 trains were eastbounds, we did send some power to get the westbound and ran it down through Liberty Center and west. There are just to many trains behind them to pull them back.
Well, with the chance of something happening at Porter with 100 trains per day is pretty slim: Approximately a 1 in 10,000,000 in fact (we checked the records).